Groundbreaking May 20, 2004
REPLACEMENT RANCHO HIGH SCHOOL
Construction Update Winter 2005
TO OUR STUDENTS, PARENTS, ALUMNI AND COMMUNITY:
Construction is on schedule for completion
in May 2006
Replacement Rancho High School will open in
August 2006
Steel framing is nearly 80 percent complete
Second floor slab on deck has been poured
Electrical, mechanical and plumbing rough is
ongoing
Memorial wall, cornerstone and jet monument
in design
Scope of $75 million project includes:
330,000-square-foot mall-style high school
Organized into four academic houses
73 classrooms
14 science labs
5 computer labs
3 art studios, plus photography studio
2 family and consumer science labs
Drafting technology lab
Automotive technology lab
120-seat lecture hall
Medical and aviation magnet program special
facilities
2,700-seat gymnasium
300-seat auxiliary gymnasium
Wrestling, dance, weight rooms and locker room
facilities
State-of-the-art, 460-seat theater
Drama room and backstage facilities
Enhanced classrooms for band, orchestra, choir
programs
REPLACEMENT PHASE II
Work on athletic fields is scheduled to start
on July 3, 2006
Scope of work includes:
5,000-seat football stadium
Three concession/restroom buidlings
Baseball field
Softball field
Practice field
8 tennis courts
5 basketball court

Reconstructed breezeway |

New classroom |